Fenlon Parking Garage

Client

Steiner + Associates

Location

Easton Town Center - Columbus, Ohio

Architect

M+A Architects

Overview

New construction of a 1,046 space parking garage to replace an existing surface lot. The new garage includes four levels of parking, 30,000 SF first floor retail and a basement retention level. 17,000 cubic yards of concrete, 920 tons of reinforcement steel and 260 tons of post-tensioning.

The team devised an ingenious plan to ‘stair-step’ the construction of the garage in four vertical sections, versus the traditional method of building first floor then second floor, etc., going up per horizontal floor.